§ Technical brief

TidalCore — concept-stage technical brief

A study of a compact heat-pipe microreactor for maritime hubs, evaluating shore power and high-temperature process heat for hard-to-electrify port operations. Every figure below is a concept target or study assumption.

Hardware status — No TidalCore reactor hardware has been built, fuelled, or tested. 15 MWth, ~850 °C, and every other parameter published here are concept targets and study assumptions from reduced-order models, pending independent validation.

1. Concept targets

Thermal power
15 MWth (concept target)
Electrical output
5.0 MWe net, electric-priority (~5.3 MWe gross, ~6% house load)
Efficiency
~35.5% gross / ~33% net sCO₂ cycle (concept target)
Cogeneration option
~6 MWth process heat + ~3 MWe net (never above 15 MWth total)
Core life
12-year target core
Core outlet temperature
~850 °C (concept target)
Primary heat transport
Sodium heat pipes (passive, no pumped primary coolant)
Fuel
HALEU TRISO particle fuel (supply not secured)
Power conversion
Supercritical CO₂ Brayton cycle (study assumption)
Module
Factory-sealed, transportable (study assumption)

2. Deployment phases

  • Phase 1 — electricity-only export to a port MV substation for shore power and microgrid loads.
  • Phase 2 — co-located high-temperature process heat, only after Phase 1 protocols exist.

3. Port siting envelope

Module footprint
~180 m² per module (study assumption)
Excludes switchgear, security buildings and laydown.
Security & controlled area
To be set by site-specific analysis
Standoff and exclusion distances are an open licensing question under Part 53 and NRC security rules — not assumed here.
Siting options
Quay-side (on land) or barge-mounted
Barge option would need adequate berth water depth and mooring; depth is port-specific.
Grid connection
Port MV substation, 6.6 kV / 11 kV class
Typical shore-power voltages; exact interface depends on the host port.
Crane & berth clearance
Sited outside crane rail and berth operating envelope
Placement is a planning assumption to avoid disrupting cargo operations.
Natural hazards
Seismic, flooding, storm surge and tsunami screening required
No site has been characterised; design-basis hazards are unknown.

4. Proposed licensing pathway (NRC 10 CFR Part 53, effective 2026-04-29)

  1. NRC pre-application engagement — not started
  2. Part 53 conformance gap analysis — planning assumption
  3. Design-stage application route — open question
  4. USCG / host-port interface protocol — not started
  5. Site-specific licensing at a host port — target, no host port

TidalCore holds no licence, approval, fuel allocation, port agreement or partnership. Nothing here guarantees any technical, regulatory or funding outcome. More detail: specifications, regulatory pathway, data room.